Company or firm · 2 projects · 3 MahaRERA registrations

Also appears as Issued to Runwal Real Estates Private Limited

2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
7 MahalaxmiPR1170002400011Ward Gsouth2024Certificate Signed31 Oct 203129 Feb 2032+4 months
7 Mahalaxmi - Tower 2P51900079270Ward Gsouth2025Certificate Signed31 Oct 203129 Feb 2032+4 months
7 MahalaxmiPR1172022600440Ward Gsouth2026Certificate Signed30 Sep 203430 Jan 2035+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • 7 Mahalaxmi+4 mo
  • 7 Mahalaxmi - Tower 2+4 mo
  • 7 Mahalaxmi+4 mo

Track record notes

  • Longest extension on record: 4 months, for 7 Mahalaxmi (PR1170002400011).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology