Runwal Developers Private Limited
Company or firm · 5 projects · 6 MahaRERA registrations
Also appears as RUNWAL DEVELOPERS PVT LTD · Runwal Realty Private Limtied · Runwal Realty Pvt Ltd
Projects56 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%4 of 6 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Runwal ElinaP51800000072 | Kurla | 2017 | Not reported | 31 Dec 2018 | 31 Dec 2018 | On date |
| Runwal ReserveP51900000383 | Mumbai City | 2017 | Not reported | 31 Dec 2019 | 31 Dec 2019 | On date |
| Runwal Elegante - Tower AP51800003620 | Andheri | 2017 | Not reported | 30 Mar 2020 | 31 Dec 2023 | +45 months |
| Runwal Eirene - Part IP51700004574 | Thane | 2017 | Not reported | 30 Jun 2025 | — | On date |
| The ResidenceP51900011063 | Ward Abcd | 2017 | Not reported | 30 Dec 2020 | — | On date |
| Runwal ElinaP51800017502 | Kurla | 2018 | Not reported | 30 Dec 2022 | 30 Dec 2023 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 45 months, for Runwal Elegante - Tower A (P51800003620).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 4 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology