Rsm Homes Llp

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases1MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Rsm NiyatiP52000002549Bokadvira2017Not reported30 Sep 2020—On date
Unimont CoralP52000002634Bokadvira2017Not reported30 Dec 202231 Dec 2027+60 months
OpalP52000018118Bokadvira2018Not reported30 Dec 2023—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Rsm NiyatiOn date
  • Unimont Coral+60 mo
  • OpalOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 60 months, for Unimont Coral (P52000002634).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology