Rozi Construction And Developers
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Rozi Pushpa SagarP52800006682 | Chiplun (M Cl) | 2017 | Not reported | 30 Mar 2021 | 30 Jun 2022 | +15 months |
| Kavita HeightsP52800015846 | Chiplun (M Cl) | 2018 | Not reported | 1 Nov 2023 | — | On date |
| Fatima HeightsP52800034623 | Chiplun (M Cl) | 2022 | Not reported | 12 Dec 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 15 months, for Rozi Pushpa Sagar (P52800006682).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology