Royal Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+24 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Utsav ResidencyP52100006886Wagholi2017Not reported17 Jun 2019—On date
Utsav Business CenterP52100018719Wagholi2018Not reported30 Mar 202230 Mar 2024+24 months
Utsav Residency Phase IIP52100019080Wagholi2019Not reported30 Sep 202130 Nov 2023+26 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Utsav ResidencyOn date
  • Utsav Business Center+24 mo
  • Utsav Residency Phase II+26 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 26 months, for Utsav Residency Phase II (P52100019080).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology