Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as Roswalt Realty Private Limited

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
72 MaheshwardhamP51800027418Kurla2020Certificate Signed30 Apr 202630 Apr 2026On date
Sujata NivasPR1180002600645Bandra2026Not reported25 Oct 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • 72 MaheshwardhamOn date
  • Sujata NivasOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology