Rose Dream Developers
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Rose GalaxyP52100006411 | Pimpri Chinchawad (M Corp.) | 2017 | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| Rose GardeniaP52100019495 | Kiwale | 2019 | Not reported | 30 Jan 2024 | 30 Sep 2026 | +32 months |
| Rose Gardenia Phase IIP52100035063 | Pimpri Chinchawad (M Corp.) | 2022 | Not reported | 30 Sep 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 32 months, for Rose Gardenia (P52100019495).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology