Rohan Developers Pvt. Ltd

Company or firm · 4 projects · 4 MahaRERA registrations

Also appears as Rohan Developers Pvt Ltd · Rohan Developers Pvt. Ltd.

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date25%1 of 4 past their proposed date, not extended
Median delay+7 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Lifescapes MirageP51900001725Ward Gnorth2017Not reported31 Dec 201731 Mar 2018+3 months
Lifescapes AmbarP51900001899Ward Gsouth2017Not reported31 Dec 2018—On date
Lifescapes ShubhamP51900002696Ward Abcd2017Not reported29 Jun 202431 May 2025+11 months
Lifescapes ArihantP51900005185Ward Abcd2017Not reported30 Dec 202231 Jan 2025+25 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Lifescapes Mirage+3 mo
  • Lifescapes AmbarOn date
  • Lifescapes Shubham+11 mo
  • Lifescapes Arihant+25 mo

Track record notes

  • 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 25 months, for Lifescapes Arihant (P51900005185).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology