Rohan Construction
Company or firm · 2 projects · 2 MahaRERA registrations
Also appears as M/S ROHAN CONSTRUCTION
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Zp Hill Wing D G HP51700011140 | Ambarnath(M Cl) | 2017 | Not reported | 30 Jun 2021 | 30 Sep 2022 | +15 months |
| Krishna Highlands Phase 1P51700045328 | Ambarnath(M Cl) | 2022 | Not reported | 31 Dec 2025 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 15 months, for Zp Hill Wing D G H (P51700011140).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology