Rohan & Atul Enterprises
Company or firm · 3 projects · 4 MahaRERA registrations
3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Rohan IpsitaP52100017870 | Hinjavadi (Ct) | 2018 | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | On date |
| Rohan AnanyaP52100023321 | Hinjavadi (Ct) | 2019 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Rohan NiditaP52100050746 | Mulshi | 2023 | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 months |
| Rohan NiditaP52100078282 | Mulshi | 2024 | Not reported | 31 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Rohan Nidita (P52100050746).
Regulatory cases across projects
- DeregisteredDeregistered: Rohan Ananya · Rohan Ananya · P52100023321
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology