Riverview City Constructions Ltd
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Falcon Towers at Riverview CityP52100032051 | Kadamwak Wasti | 2021 | Not reported | 2 Jun 2025 | — | On date |
| Skylark Apartments RVR 7A at Riverview CityP52100047628 | Kadamwak Wasti | 2022 | Not reported | 31 Mar 2026 | — | On date |
| Hornbill Heights at Riverview CityP52100053795 | Kadamwak Wasti | 2023 | Not reported | 31 Dec 2027 | — | On date |
| Flamingo ParkPR1260002600177 | Kadamwak Wasti | 2026 | Not reported | 31 Jul 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology