Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%2 of 4 past their proposed date, not extended
Median delay+5 movs RERA proposed date · 2 extended
Regulatory cases1MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Hi LifeP52100016413Thergaon2018Not reported30 Jun 202331 Mar 2025+21 months
Hi Life phase 2P52100017433Thergaon2018Not reported30 Jun 2024—On date
hi life phase3P52100017456Thergaon2018Not reported30 Jun 202429 Mar 2025+9 months
AltitudeP52100024885Thergaon2020Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Hi Life+21 mo
  • Hi Life phase 2On date
  • hi life phase3+9 mo
  • AltitudeOn date

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 21 months, for Hi Life (P52100016413).