Rishikesh Builders & Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Also appears as RISHIKESH BUILDERS AND DEVELOPERS

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nandlal PlazaP51600023461Nashik2019Not reported30 Mar 202331 Mar 2024+12 months
Tulasi BaugP51600026532Nashik Road2020Not reported31 Dec 2027—On date
Tulasi BaugP51600027664Nashik Road2020Not reported31 Dec 202731 Dec 2027On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nandlal Plaza+12 mo
  • Tulasi BaugOn date
  • Tulasi BaugOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Nandlal Plaza (P51600023461).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology