Renuka Realtors

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+24 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ruparel JewelP51900003058Mumbai City2017Not reported31 Dec 202231 Dec 2026+48 months
Ruparel MillenniaP51900031698Mumbai City2021Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ruparel Jewel+48 mo
  • Ruparel MillenniaOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 48 months, for Ruparel Jewel (P51900003058).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology