Renuka Constructions

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gaurav ParkP52100012750Talegaon Dabhade (M Cl)2017Certificate Signed30 Sep 201930 Sep 2022+36 months
Shrushti ApartmentP52100012811Talegaon Dabhade (M Cl)2017Certificate Signed30 Sep 201930 Sep 2019On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gaurav Park+36 mo
  • Shrushti ApartmentOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 36 months, for Gaurav Park (P52100012750).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology