Renaissance Enterprises
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| TreemountP52100015410 | Talegaon Dabhade (R) | 2018 | Certificate Signed | 30 Jun 2018 | 30 Jun 2019 | +12 months |
| Spring FieldP51800023731 | Borivali | 2020 | Not reported | 30 Jun 2022 | 30 Jun 2023 | +12 months |
| Spring MeadowsP51800033680 | Borivali | 2022 | Not reported | 31 Dec 2024 | 30 Dec 2026 | +24 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 24 months, for Spring Meadows (P51800033680).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology