Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
TreemountP52100015410Talegaon Dabhade (R)2018Certificate Signed30 Jun 201830 Jun 2019+12 months
Spring FieldP51800023731Borivali2020Not reported30 Jun 202230 Jun 2023+12 months
Spring MeadowsP51800033680Borivali2022Not reported31 Dec 202430 Dec 2026+24 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Treemount+12 mo
  • Spring Field+12 mo
  • Spring Meadows+24 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Spring Meadows (P51800033680).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology