Reliable Constructions
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+24 movs RERA proposed date · 2 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| VASUNDHARA CHS LTD - Phase II - A and B WingP51800005777 | Borivali | 2017 | Not reported | 31 Dec 2019 | 30 Dec 2021 | +24 months |
| Laxmi NagarP51800010918 | Borivali | 2017 | Not reported | 30 Dec 2023 | 31 Dec 2026 | +36 months |
| Shastri Nagar Prabhat Chsl Phase II A And B WingP51800033876 | Borivali | 2022 | Not reported | 31 Dec 2025 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 36 months, for Laxmi Nagar (P51800010918).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: LAXMI NAGAR (Regulatory Case No. 350 OF 2025) dated 18 June, 2025. · Laxmi Nagar · P51800010918 · 18 Jun 2025