Reliable Constructions

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+24 movs RERA proposed date · 2 extended
Regulatory cases1MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
VASUNDHARA CHS LTD - Phase II - A and B WingP51800005777Borivali2017Not reported31 Dec 201930 Dec 2021+24 months
Laxmi NagarP51800010918Borivali2017Not reported30 Dec 202331 Dec 2026+36 months
Shastri Nagar Prabhat Chsl Phase II A And B WingP51800033876Borivali2022Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • VASUNDHARA CHS LTD - Phase II - A and B Wing+24 mo
  • Laxmi Nagar+36 mo
  • Shastri Nagar Prabhat Chsl Phase II A And B WingOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 36 months, for Laxmi Nagar (P51800010918).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology