Relcon Zp Je Construction Llp

Company or firm · 1 project · 1 MahaRERA registration

Also appears as M/S. Relcon Zp Je Construction Llp

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
103 WestP51800066510Eksar2024Certificate Signed31 Mar 202931 Jul 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • 103 West+4 mo

Track record notes

  • Longest extension on record: 4 months, for 103 West (P51800066510).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology