Rekha Subhash Jagdale

Individual promoter · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai GreensP52000003773Palaspe2017Certificate Signed31 Dec 202531 Dec 2025On date
Sai GardensP52000005728Karjat2017Certificate Signed31 Dec 202531 Dec 2025On date
Sai Greens C WingP52000055820Palaspe2024Certificate Signed31 Dec 202631 Dec 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai GreensOn date
  • Sai GardensOn date
  • Sai Greens C WingOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.

Regulatory cases across projects