Regent Builders
Company or firm · 6 projects · 6 MahaRERA registrations
6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Saket Residency Co Op Hsg Soc LtdP51800007061 | Andheri | 2017 | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
| Audumbar Chs LtdP51800015235 | Andheri | 2018 | Certificate Signed | 30 Mar 2022 | 30 Mar 2022 | On date |
| Om Madhusadan Chs LtdP51800034194 | Andheri | 2022 | Certificate Signed | 31 Mar 2025 | 31 Mar 2025 | On date |
| Jeevan Tara CHS LTDP51800049161 | Vileparle | 2023 | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
| Regent Aparna MahalP51800077501 | Vileparle | 2024 | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 months |
| Regent Kashi KunjP51800077648 | Vileparle | 2024 | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Regent Aparna Mahal (P51800077501).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology