Skip to content

Reddy Builders & Developers

Company or firm · 1 project · 1 MahaRERA registration

Also appears as M/S REDDY BUILDERS & DEVELOPERS

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
34 Park EstateP51800006729Borivali2017Certificate Signed31 Jul 202830 Nov 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • 34 Park Estate+4 mo

Track record notes

  • Longest extension on record: 4 months, for 34 Park Estate (P51800006729).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology