Rays Infra
Company or firm · 2 projects · 2 MahaRERA registrations
Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Lake Homes Wing BP52100003515 | Ambegaon Kh | 2017 | Not reported | 31 Mar 2018 | — | On date |
| Lake Homes Wing AP52100004836 | Ambegaon Kh | 2017 | Not reported | 1 Jul 2018 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology