Raymond Limited
Company or firm · 10 projects · 11 MahaRERA registrations
10Projects11 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date9 of 9 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| TEN X HABITAT Raymond Realty | Tower A & BP51700019265 | Thane | 2019 | Certificate Signed | 30 Mar 2025 | 30 Mar 2025 | On date |
| TEN X HABITAT Raymond Realty Tower CP51700020256 | Thane (M Corp.) | 2019 | Certificate Signed | 30 Mar 2025 | 30 Mar 2025 | On date |
| TEN X HABITAT Raymond Realty Tower DP51700020881 | Thane | 2019 | Certificate Signed | 30 Sep 2025 | 30 Sep 2025 | On date |
| TEN X HABITAT Raymond Realty Tower EP51700022779 | Thane | 2019 | Certificate Signed | 30 Sep 2025 | 30 Sep 2025 | On date |
| TEN X HABITAT Raymond Realty Tower KP51700022940 | Thane | 2019 | Certificate Signed | 30 Sep 2025 | 30 Sep 2025 | On date |
| TEN X HABITAT Raymond Realty Tower JP51700025355 | Thane | 2020 | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | On date |
| TEN X HABITAT Raymond Realty Tower HP51700027036 | Thane (M Corp.) | 2020 | Certificate Signed | 30 Sep 2025 | 30 Sep 2025 | On date |
| The Address by GSP51700031762 | Thane (M Corp.) | 2021 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| AashiyanaP51700045709 | Thane | 2022 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| The Address by GSP51700045829 | Thane (M Corp.) | 2022 | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 months |
| Ten X VibesP51700052442 | Thane (M Corp.) | 2023 | Certificate Signed | 31 May 2024 | 31 May 2024 | On date |
Show all 11 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 11 registrations
Track record notes
- 9 of 9 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for The Address by GS (P51700031762).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology