Raviraj Bokadia Creative
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 3 past their proposed date, not extended
Median delay+18 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| 93 Avenue Phase- 1P52100015538 | Pune (M Corp.) | 2018 | Not reported | 31 Mar 2019 | 30 Sep 2020 | +18 months |
| 93 Avenue Phase-IIP52100017392 | Pune (M Corp.) | 2018 | Not reported | 31 Mar 2019 | 30 Sep 2020 | +18 months |
| 93 Avenue Phase- IIIP52100019662 | Pune (M Corp.) | 2019 | Not reported | 17 Nov 2019 | 16 Nov 2021 | +24 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 24 months, for 93 Avenue Phase- III (P52100019662).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology