Raviraj Bokadia Creative

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 3 past their proposed date, not extended
Median delay+18 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
93 Avenue Phase- 1P52100015538Pune (M Corp.)2018Not reported31 Mar 201930 Sep 2020+18 months
93 Avenue Phase-IIP52100017392Pune (M Corp.)2018Not reported31 Mar 201930 Sep 2020+18 months
93 Avenue Phase- IIIP52100019662Pune (M Corp.)2019Not reported17 Nov 201916 Nov 2021+24 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • 93 Avenue Phase- 1+18 mo
  • 93 Avenue Phase-II+18 mo
  • 93 Avenue Phase- III+24 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for 93 Avenue Phase- III (P52100019662).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology