Ravindrasingh Girwarsingh Janewar, Tara Mahadev Thakur, Shivam Ajaysingh Vyas
Company or firm · 1 project · 1 MahaRERA registration
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sh.ravindrasingh Girwarsingh Janewar Smt. Tarabai Mahadeo Thakur And Sh. Shivam Ajaysingh VyasP50500055250 | Pewatha | 2024 | Not reported | 31 Mar 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
