Ravindra Developers Pvt Ltd

Company or firm · 6 projects · 6 MahaRERA registrations

Also appears as M/S. Ravindra Developers Pvt. Ltd. · Ravindra Developers Private Limited

Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%4 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Ravi EnclaveP51600011917Nashik (M Corp.)2017Not reported31 Dec 2019—On date
Ravi RenaissanceP51600012691Nashik (M Corp.)2017Not reported31 Dec 2019—On date
Ganadhish ParkP51600030411Nashik (M Corp.)2021Not reported30 Jun 2024—On date
Aura Sky TowerP51600047853Nashik (M Corp.)2022Not reported3 Feb 2027—On date
Yogesh Co-Operative Housing SocietyP51600048451Nashik (M Corp.)2023Not reported31 Dec 2025—On date
Morya ParkP51600077536Nashik (M Corp.)2024Not reported31 Mar 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Ravi EnclaveOn date
  • Ravi RenaissanceOn date
  • Ganadhish ParkOn date
  • Aura Sky TowerOn date
  • Yogesh Co-Operative Housing SocietyOn date
  • Morya ParkOn date

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology