Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as Ranjeet Property Developers India Pvt. Ltd.

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+30 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Platinum Park Phase IIP52100007013Undri2017Not reported30 Dec 202231 Dec 2026+48 months
Platinum Park Phase IP52100007249Undri2017Not reported31 Dec 201831 Dec 2019+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Platinum Park Phase II+48 mo
  • Platinum Park Phase I+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 48 months, for Platinum Park Phase II (P52100007013).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.