Ranjeet Harishchandra Khandge
Individual promoter · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| ShivayP52100014761 | Talegaon Dabhade (M Cl) | 2018 | Not reported | 31 Mar 2019 | — | On date |
| ViharP52100023196 | Talegaon Dabhade (M Cl) | 2019 | Not reported | 30 Dec 2021 | — | On date |
| Aastha ResidencyP52100032170 | Talegaon Dabhade (M Cl) | 2021 | Not reported | 20 Apr 2023 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
