Rajesh Construction

Company or firm · 6 projects · 7 MahaRERA registrations

6Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
80%Kept RERA date4 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mahavir Krupa DP99000000244Saravali2017Certificate Signed31 Dec 201731 Dec 2017On date
Mahavir Utsav BP99000015701Pasthal2018Certificate Signed31 Oct 201931 Oct 2019On date
Mahavir SadanP99000021076Palghar2019Certificate Signed30 Jun 202130 Apr 2022+10 months
Mahavir SadanP99000028787Palghar2021Certificate Signed30 Dec 202330 Dec 2023On date
Mahavir KutirP99000046061Pasthal2022Certificate Signed31 Dec 202531 Dec 2025On date
Mahavir NeytraP99000048189Pasthal2022Certificate Signed31 Dec 202731 Dec 2027On date
Mahavir TirthPR1240002601570Pasthal2026Certificate Signed31 Dec 203231 Dec 2032On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mahavir Krupa DOn date
  • Mahavir Utsav BOn date
  • Mahavir Sadan+10 mo
  • Mahavir SadanOn date
  • Mahavir KutirOn date
  • Mahavir NeytraOn date
  • Mahavir TirthOn date

Track record notes

  • 4 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 10 months, for Mahavir Sadan (P99000021076).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology