Rajendra Surana
Individual promoter · 1 project · 1 MahaRERA registration
Also appears as Rajendra Surana
Projects11 RERA registration
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+70 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Neeraj ViharP51500011515 | Aurangabad (M Corp.) | 2017 | Not reported | 30 Aug 2019 | 30 Jun 2025 | +70 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 70 months, for Neeraj Vihar (P51500011515).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology