Rahul Baban Kamble
Individual promoter · 2 projects · 2 MahaRERA registrations
Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+24 movs RERA proposed date · 1 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Omkar ComplexP52100027276 | Kasar Amboli | 2020 | Not reported | 30 Jun 2022 | 30 Jun 2026 | +48 months |
| Omkar HeightsP52100030932 | Kasar Amboli | 2021 | Not reported | 30 Jun 2026 | 30 Jun 2026 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 48 months, for Omkar Complex (P52100027276).
Regulatory cases across projects
- Quarterly progress report not filedQuarterly progress report not filed: OMKAR HEIGHTS · Omkar Heights · P52100030932
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology