Raghvendra Buildcon

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Akashvedh Phase 1P52100006065Pimpri Chinchawad (M Corp.)2017Certificate Signed31 Dec 201831 Dec 2019+12 months
Akashvedh Phase 2P52100025282Pimpri Chinchawad (M Corp.)2020Certificate Signed30 Dec 202331 Dec 2026+36 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Akashvedh Phase 1+12 mo
  • Akashvedh Phase 2+36 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 36 months, for Akashvedh Phase 2 (P52100025282).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology