Raghunath & Sons Promoters & Builders

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
AmaraP52100046563Dhayari (Part)2022Certificate Signed30 Sep 202430 Sep 2024On date
AmaraP52100055062Dhayari (Part)2024Certificate Signed31 Mar 202631 Jul 2026+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • AmaraOn date
  • Amara+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Amara (P52100055062).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology