Radhe Developers
Company or firm · 4 projects · 4 MahaRERA registrations
Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Govinda HeightsP51600004718 | Nashik | 2017 | Not reported | 30 Jun 2019 | — | On date |
| Govinda PrideP51600031509 | Nashik (M Corp.) | 2021 | Not reported | 31 Aug 2024 | — | On date |
| Govinda PlazaP51600045347 | Nashik (M Corp.) | 2022 | Not reported | 31 Dec 2024 | 30 Jun 2025 | +6 months |
| Govinda HarmonyPR1220002502859 | Nashik | 2026 | Not reported | 31 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 6 months, for Govinda Plaza (P51600045347).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology