Rachana Lifespaces
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| BellacasaP52100002878 | Sus | 2017 | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Bellacasa Royale Tower / Type 'a'P52100027124 | Mulshi | 2020 | Certificate Signed | 1 Jun 2027 | 1 Jun 2027 | On date |
| Bellacasa Royale Tower B/ Type BP52100030088 | Mulshi | 2021 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Rachana Business Bay Commercial 2P52100050723 | Mulshi | 2023 | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology