0Completedas reported on MahaRERA project pages
71%Kept RERA date5 of 7 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Rachana SamruddhiP50500008630 | Pipla | 2017 | Not reported | 31 Jul 2023 | — | On date |
| Rachana Mithila IIP50500019742 | Pipla | 2019 | Not reported | 31 Dec 2019 | 30 Dec 2021 | +24 months |
| Rachana AshwiniP50500020724 | Borgaon Khu. | 2019 | Not reported | 30 Apr 2022 | — | On date |
| Rachana AnandvanP50500025865 | Wanadongri | 2020 | Not reported | 31 Mar 2021 | — | On date |
| Rachana Mithila IIIP50500027382 | Pipla | 2020 | Not reported | 30 Jun 2022 | — | On date |
| Rachana RohiniP50500033105 | Borgaon Khu. | 2022 | Not reported | 30 Jun 2024 | 30 Nov 2024 | +5 months |
| Rachana PurvaP50500053221 | Nagpur (M Corp.) | 2023 | Not reported | 30 Sep 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 24 months, for Rachana Mithila II (P50500019742).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology