Rachana Developers

Company or firm · 7 projects · 7 MahaRERA registrations

7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
71%Kept RERA date5 of 7 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Rachana SamruddhiP50500008630Pipla2017Not reported31 Jul 2023—On date
Rachana Mithila IIP50500019742Pipla2019Not reported31 Dec 201930 Dec 2021+24 months
Rachana AshwiniP50500020724Borgaon Khu.2019Not reported30 Apr 2022—On date
Rachana AnandvanP50500025865Wanadongri2020Not reported31 Mar 2021—On date
Rachana Mithila IIIP50500027382Pipla2020Not reported30 Jun 2022—On date
Rachana RohiniP50500033105Borgaon Khu.2022Not reported30 Jun 202430 Nov 2024+5 months
Rachana PurvaP50500053221Nagpur (M Corp.)2023Not reported30 Sep 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Rachana SamruddhiOn date
  • Rachana Mithila II+24 mo
  • Rachana AshwiniOn date
  • Rachana AnandvanOn date
  • Rachana Mithila IIIOn date
  • Rachana Rohini+5 mo
  • Rachana PurvaOn date

Track record notes

  • 5 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Rachana Mithila II (P50500019742).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology