Rabbani Khan
Individual promoter · 5 projects · 5 MahaRERA registrations
Also appears as Rabbani khan
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shelter ParadiseP52000010402 | Kharghar | 2017 | Certificate Signed | 1 Apr 2021 | 30 Sep 2024 | +41 months |
| Shelter RiversideP52000012021 | Taloje Panchnad | 2017 | Certificate Signed | 1 Nov 2020 | 1 Nov 2020 | On date |
| Shelter CornerP52000010366 | Taloje Panchnad | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Shelter ViewP52000029498 | Taloje Panchnad | 2021 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Shelter DreamP52000049410 | Taloje Majkur | 2023 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 41 months, for Shelter Paradise (P52000010402).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology