R Retail Ventures Private Limited
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| The Central Park Phase -IP52100025260 | Haveli | 2020 | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 months |
| The Central Park Phase - IIP52100030291 | Haveli | 2021 | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 months |
| The Central Park Phase - IIIP52100032101 | Haveli | 2021 | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 months |
| The Central Park Phase - IV Tower D4PR1260002502733 | Chinchwad | 2026 | Certificate Signed | 15 Dec 2031 | 15 Apr 2032 | +4 months |
| The Central Park Phase- IV Tower D3PR1260002503069 | Chinchwad | 2026 | Certificate Signed | 31 May 2031 | 30 Sep 2031 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for The Central Park Phase -I (P52100025260).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology