R D Developers
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+7 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Ganesh Prime VeraP52100033593 | Pune (M Corp.) | 2022 | Not reported | 31 Dec 2024 | 31 Jul 2025 | +7 months |
| Ganesh Prime Vera Building AP52100033844 | Pune (M Corp.) | 2022 | Not reported | 31 Dec 2024 | 31 Jul 2025 | +7 months |
| Tsb GloriaPR1260002600292 | Pune (M Corp.) | 2026 | Not reported | 30 Apr 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 7 months, for Ganesh Prime Vera (P52100033593).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology