Qualitas Naman Home Makers Llp

Company or firm · 2 projects · 4 MahaRERA registrations

2Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Qn GreensP52000007707Koyana Velhe2017Not reported31 Dec 201930 Dec 2021+24 months
Qn GreensP52000015726Koyana Velhe2018Not reported30 Jun 202130 Jun 2022+12 months
Qn GreensP52000018224Koyana Velhe2018Not reported30 Dec 2022—On date
QN HeightsP52000021242Taloje Majkur2019Not reported30 Dec 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Qn Greens+24 mo
  • Qn Greens+12 mo
  • Qn GreensOn date
  • QN HeightsOn date

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Qn Greens (P52000007707).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology