Pyramid Developers

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shri HimgiriP52000012130Panvel2017Not reported31 May 201930 Sep 2024+64 months
SnehabandhP52000033534Panvel2022Not reported30 Jun 2025—On date
PratapnagarP52000078692Panvel2025Not reported31 Dec 2026—On date
NalandaP52000078806Panvel2025Not reported31 Aug 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shri Himgiri+64 mo
  • SnehabandhOn date
  • PratapnagarOn date
  • NalandaOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 64 months, for Shri Himgiri (P52000012130).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology