Pyramid Arcades Pvt Ltd

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Pyramid City 5P50500005437Pipla2017Not reported30 Sep 201830 Sep 2019+12 months
Pyramid city 1P50500012106Nagpur (M Corp.)2017Not reported31 Dec 2017—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Pyramid City 5+12 mo
  • Pyramid city 1On date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Pyramid City 5 (P50500005437).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology