Pushpendra Real Construction Private Limited
Company or firm · 5 projects · 7 MahaRERA registrations
Projects57 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Pushpendra City- Mahalakshmi PresidencyP52800000951 | Khedshi | 2017 | Not reported | 30 Dec 2020 | 30 Jun 2022 | +18 months |
| Pushpendra CityP52800000964 | Khedshi | 2017 | Not reported | 30 Jun 2028 | — | On date |
| Pushpendra City - Sector 4P52800001012 | Khedshi | 2017 | Not reported | 30 Jun 2028 | — | On date |
| Pushpendra City- Mahalakshmi EnclaveP52800001072 | Khedshi | 2017 | Not reported | 30 Jun 2022 | — | On date |
| Pushpendra CityP52800001114 | Khedshi | 2017 | Not reported | 30 Jun 2028 | — | On date |
| Pushpendra CityP52800001505 | Khedshi | 2017 | Not reported | 30 Jun 2028 | — | On date |
| Mahalakshmi ResidencyP52800030838 | Karvanchiwadi | 2021 | Not reported | 12 Mar 2025 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Pushpendra City- Mahalakshmi Presidency (P52800000951).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology