Puravankara Limited

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date—no proposed date has passed yet
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Purva Clermont Wing EP51800028492Mumbai2021Not reported30 Jun 2027—On date
Purva Clermont Wing DP51800028494Mumbai2021Not reported30 Jun 2027—On date
Purva Clermont Wing AP51800028571Mumbai2021Not reported30 Jun 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Purva Clermont Wing EOn date
  • Purva Clermont Wing DOn date
  • Purva Clermont Wing AOn date

Track record notes

  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology