Skip to content
Deedo home
Menu

Puneet Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Puneet Developers - Tanishq F And G WingP99000032306Vangaon2021Certificate Signed31 Jul 202531 Jul 2025On date
Tanishq H And I WingP99000047114Vangaon2022Certificate Signed31 Dec 202631 Dec 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Puneet Developers - Tanishq F And G WingOn date
  • Tanishq H And I WingOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology