Pune Buildtech Private Limited

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+24 movs RERA proposed date · 2 extended
Regulatory cases3MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
DB Commercial Phase IIP52100003455Pune (M Corp.)2017Not reported31 Dec 201930 Dec 2021+24 months
DB Commercial Phase IP52100004589Pune (M Corp.)2017Not reported1 Dec 201928 Nov 2021+23 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • DB Commercial Phase II+24 mo
  • DB Commercial Phase I+23 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for DB Commercial Phase II (P52100003455).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology