Proviso Builders And Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+18 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai Proviso CountyP51700002042Shirdhon2017Not reported30 Jun 202131 Dec 2023+30 months
Sai Proviso SapphireP52000021378Rodpali2019Not reported30 Jun 202329 Dec 2024+18 months
Sai Proviso IconP52000023351Kalamboli2019Not reported30 Dec 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai Proviso County+30 mo
  • Sai Proviso Sapphire+18 mo
  • Sai Proviso IconOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 30 months, for Sai Proviso County (P51700002042).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology