Prithvi Shaurya Nirmitee India Private Limited

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+27 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Prithivi Shourya Sky OneP52100012609Pimpri Chinchawad (M Corp.)2017Not reported31 Mar 2027—On date
VrindavanP52100020791Haveli2019Not reported30 Dec 202130 Jun 2026+54 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Prithivi Shourya Sky OneOn date
  • Vrindavan+54 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 54 months, for Vrindavan (P52100020791).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology