Prithvi Land Developers
Company or firm · 2 projects · 2 MahaRERA registrations
Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date—no proposed date has passed yet
Median delay+6 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Prithvi Pride Building No 2P51700076775 | Mirabhayandar (M Corp.) | 2024 | Not reported | 31 Dec 2028 | 31 Dec 2029 | +12 months |
| Prithvi Pride Building No 3P51700077237 | Thane | 2024 | Not reported | 31 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 12 months, for Prithvi Pride Building No 2 (P51700076775).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology