Prism Infra And Developments
Company or firm · 2 projects · 2 MahaRERA registrations
Also appears as Issued to PRISM INFRA AND DEVELOPMENTS
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Menlo EstellaPC1260002400070 | Mulshi | 2024 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Menlo Hashtag StudiosP52100077996 | Hinjavadi (Ct) | 2024 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Menlo Estella (PC1260002400070).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.